CGA were appointed by the Waltham Forest college to complete the refurbishment works within the historical college building. The works were all completed in occupied areas and the project was under a tight time frame. CGA worked with the in college to ensure a smooth transition of occupant decant, completion of refurbishment through to re-occupation. all works were controlled and segregated through Hygienic hoarding and CGA worked with the in house maintenance team on key isolations on power and fire alarm systems to ensure no disruptions to the adjoining areas to allow for a continuation of the daily college activities.
Scope:
- New floor finishes in all classrooms and teaching rooms
- Introduction of new lighting systems
- Introduction of standard layout teaching walls and AV
- New Dado trunking layout with power & Data outlets
- Paint finishes throughout
- New lighting system to all class rooms
- Light refurbishment of WCs x 9
- Complete overhaul of the reception area
- Works to corridor including ceilings margins and lighting
- Complete overhaul of the student services area
- New staff kitchen
- Overhaul of existing windows
- New WC extraction system
- Branding installation