Christie's, South Kensington

Hammer
Type

Commercial Fit-out

User
Client

Christie's

Clock
Duration

23 weeks

Pound sign
Value

In 2013 CGA completed the refurbishment and fit out works to Christie’s, South Kensington basement offices and warehouse area. The project was carried out over three phases whilst the building was occupied and auctions continued. During the works the areas were decanted and repopulated in each phase.

Phase 1 consisted of the strip out and demolition of the existing warehouse which was then returned to open plan office with meeting rooms, copy areas and break out room. All new mechanical and electrical services were installed including air conditioning and new fresh air systems.

For Phase 2 we created a new open plan space with specialist automated racking system and storage units, followed by Phase 3 for which we provided new secure storage space and storage units.